Gilroy Archives - Monterey Peninsula Engineering Website https://mpe2000.info/portfolio-tag/gilroy/ Award Winning Civil Contractor in the Tri-County Area Thu, 05 Jun 2025 17:26:23 +0000 en-US hourly 1 https://wordpress.org/?v=7.1.3 https://mpe2000.info/wp-content/uploads/2022/02/cropped-MPE-Site-Icon-32x32.png Gilroy Archives - Monterey Peninsula Engineering Website https://mpe2000.info/portfolio-tag/gilroy/ 32 32 Regional Urban Water Augmentation Project https://mpe2000.info/portfolio-item/regional-urban-water-augmentation-project-mcwd/?utm_source=rss&utm_medium=rss&utm_campaign=regional-urban-water-augmentation-project-mcwd Mon, 14 Feb 2022 22:55:20 +0000 https://mpe2000.info/?post_type=portfolio-item&p=6974 Five miles of 8‐inch diameter to 16‐inch diameter DIP and PVC water line.

The post Regional Urban Water Augmentation Project appeared first on Monterey Peninsula Engineering Website.

]]>
Description:
The Project consists of constructing approximately 5 miles of 8‐inch diameter to 16‐inch diameter ductile iron and polyvinyl chloride recycled water and potable water pipeline in paved and non‐paved roadways and easements, connecting to existing pipelines, pipeline valves and appurtenances, a guided auger bore trenchless roadway crossing, twelve pressure reducing stations, and roadway paving for a complete in‐place operational system.

Owner: Marina Coast Water District

Contract Value: $8.8M

Location: Marina, CA

Project Manager: Bart Bruno

The post Regional Urban Water Augmentation Project appeared first on Monterey Peninsula Engineering Website.

]]>
First St Water Utility Improvements https://mpe2000.info/portfolio-item/first-street-water-utility-improvements-gilroy/?utm_source=rss&utm_medium=rss&utm_campaign=first-street-water-utility-improvements-gilroy Mon, 14 Feb 2022 22:18:22 +0000 https://mpe2000.info/?post_type=portfolio-item&p=6940 Water utility upgrades along Gilroy’s First Street, including new pipeline installation, valve replacement, and water service reconnections for improved infrastructure reliability.

The post First St Water Utility Improvements appeared first on Monterey Peninsula Engineering Website.

]]>
Description:
This Gilroy-based utility improvement project involved the installation of new water lines along First Street, including trenching, mechanical piping, valve replacement, and reconnection of existing water services. The work aimed to upgrade the city’s aging water infrastructure, improve system performance, and ensure long-term service reliability.

Owner: City of Gilroy

Contract Value: $5.5M

Location: Gilroy, CA

Project Manager: Bart Bruno